Japan's data center construction boom will continue well beyond 2026. A Nikkei xTECH survey of roughly 80 operators (42 valid responses) found that 24 companies plan 38 new builds and expansions through 2030. Five projects are giants exceeding 100 MW (megawatts) of power capacity, and more than half of the facilities support liquid cooling — a must for the latest GPU servers. And of the 35 projects with confirmed locations, 13 (about 40%) sit outside both Greater Tokyo and Greater Osaka (Nikkei BP, announced June 19, 2026).

Data centers in Japan have always meant Inzai in Chiba and the Osaka-Kyoto-Kobe corridor. That assumption is breaking down in 2026. Tomakomai, Ishikari, Yuzawa, Wakkanai, Oga, Futaba, Satsumasendai — the project list is full of place names that never appeared on Japan's data center map before. This article breaks down the 38 projects and the two tectonic shifts behind them: regional dispersal and the move to liquid cooling.

In Plain Terms (Beginner)

Data centers — the buildings that house AI computing — are going up all over Japan at once. Twenty-four companies plan 38 of them, opening steadily through 2030. They used to cluster around Tokyo and Osaka, but electricity there is running short, so about 40% will be built in regional areas like Hokkaido, Tohoku and Kyushu. And because the latest AI servers run too hot for air cooling, more than half of the new facilities are designed to cool servers with liquid instead.

Also see: The Structural View (Investor)
The Structural View (Investor)

A pipeline of 38 projects opening through 2030 is hard evidence that Japanese DC investment is not a one-off. Three things stand out. First, five projects top 100 MW (Colt Minoh 130 MW, NTT DATA TKY12 200 MW, etc.) — a step change in per-project scale. Second, over half are liquid-cooling-ready with reinforced floor loading, implying higher construction unit costs and demand flowing to cooling, power-receiving and electrical-equipment suppliers (HVAC, transformers, UPS, batteries). Third, regional dispersal is the flip side of power constraints, splitting into renewables-sited campuses (Tomakomai, Ishikari) and small containerized GPU sites (Yuzawa, Wakkanai, Oga). Projects with secured grid connections and power allocations carry scarcity value — land and power quotas are the real barriers to entry.

What did the survey find?

Between April 23 and May 26, 2026, Nikkei xTECH asked roughly 80 companies in the data center business about their construction plans (42 valid responses). The headline results (Nikkei BP):

ItemResult
Planned new builds and expansions24 companies, 38 projects (opening 2026-2030)
Location breakdownGreater Tokyo (incl. Chiba, Saitama) 13 / Greater Osaka (incl. Kyoto) 9 / elsewhere 13 (of 35 confirmed)
Power capacity above 100 MW5 projects
Liquid-cooling-readyMore than half, with a parallel trend toward reinforced floor loading

"Power capacity" here means the maximum electricity a facility can draw from the utility. 100 MW is roughly the demand of a mid-sized city — and considering that 10-30 MW was the domestic norm just a few years ago, per-project scale has jumped an entire tier.

What projects are in the pipeline?

Here are the most notable projects among the 38, by region, drawn from the survey responses (IT denotes IT/server power capacity).

CompanyFacility (location)Power capacityOpening
Colt DCSInzai 5 (Inzai, Chiba)28.8 MW (IT)Autumn 2028
Colt DCSYoshikawa (Yoshikawa, Saitama)80 MW (IT)End of 2029
MC Digital RealtyNRT14 (Inzai, Chiba)25 MWApril 2026
NTT DATA GroupTokyo TKY11 (Inzai, Chiba)50 MWApril 2027
NTT DATA GroupTochigi TCG11 (Tochigi Pref.)100 MW2029
NTT DATA GroupTokyo TKY12 (Inzai, Chiba)~200 MW2030 or later
STT GDC JapanSTT Tokyo 2 (Inzai, Chiba)60 MWQ4 2027
IIJShiroi Campus Phase 3 (Shiroi, Chiba)10 MW (expandable to 25 MW)Within 2026
KDDIOsaka Sakai Data Center (Sakai)Up to 48 MWJanuary 2026 (operating)
SoftBankOsaka Sakai AI Data Center (Sakai)Expanding beyond 140 MWFY2027
SC Zeus Data CentersZEUS OSA1 (Osaka Nanko)100+ MW (Phases 1-2)Q1 2028 or later
Colt DCSMinoh (tentative; Minoh, Osaka)130 MW (IT)~Spring 2030
NTT DATA GroupKeihanna OSK11 (Seika, Kyoto)30 MWFebruary 2026
SoftBankHokkaido Tomakomai AI Data Center50 MW (expanding beyond 300 MW)FY2026
Tokyu LandIshikari Renewable DC No. 1 (Ishikari, Hokkaido)15 MVAFull operation August 2026
GETWORKSYuzawa AI STATION (tentative; Yuzawa, Niigata)10 MW2026
Toyota TsushoSoya Container Data Center I (Wakkanai, Hokkaido)3 MWWithin 2027

Scanning the list, the 100 MW-plus giants are Colt Minoh (130 MW), NTT DATA's Tokyo TKY12 (~200 MW) and Tochigi TCG11 (100 MW), SC Zeus's ZEUS OSA1 (100+ MW), and SoftBank's Osaka Sakai (expanding beyond 140 MW). Tomakomai starts at 50 MW but plans to grow past 300 MW.

The Inzai cluster in Chiba remains as strong as ever, with five or more entries — NRT14, TKY11, TKY12, STT Tokyo 2 and IIJ Shiroi. We explain how Inzai became Japan's number one data center town in why Inzai in Chiba became Japan's data center capital (in Japanese).

Why are data centers going up in regional Japan?

Thirteen of the 35 confirmed locations sit outside Tokyo and Osaka — and this dispersal is not a change in taste but a consequence of power constraints. Spare transmission capacity around Tokyo and Osaka has thinned out, and locking in a new 100 MW-class power allocation gets harder every year. In short, data centers have started moving to where the electricity is.

Hokkaido leads the way. SoftBank and IDC Frontier's Hokkaido Tomakomai AI Data Center is one of Japan's largest plans — a roughly 700,000-square-meter site with an ultimate power capacity above 300 MW — designed to run entirely on Hokkaido-generated renewable energy, opening in FY2026 (SoftBank, April 2025). In Ishikari, Sakura Internet has operated since 2011, and Kyocera Communication Systems' Zero Emission Data Center Ishikari, opened in October 2024, combines offshore wind and its own solar to achieve Japan's first 24/7 renewable operation (Kyocera CS). The survey adds Tokyu Land's Ishikari Renewable Data Center No. 1 (full operation August 2026) and an NTT East containerized facility — Ishikari is becoming Japan's renewables-times-data-center cluster.

The other current is small containerized GPU data centers. GETWORKS operates liquid-cooled container data centers in Yuzawa, Niigata, scaling toward 110 units (Cloud Watch, February 2026). Toyota Tsusho plans the Soya Container Data Center in Wakkanai and has invested in GPU cloud provider Highreso (which runs sites in Shika, Ishikawa and Takamatsu, Kagawa) (Toyota Tsusho, July 2025). Highreso plans new sites in Oga, Akita and Ayagawa, Kagawa. Using snow and cold air for cooling, building small and fast where the grid has headroom — the exact opposite of the giant-campus model.

For the full picture of where Japan's data centers cluster today, see our national map in Japan Data Center Map: Almost Everything Sits in Just a Dozen Locations.

Why are more than half liquid-cooling-ready?

The survey's other standout finding: more than half of planned facilities support liquid cooling — carrying server heat away directly with liquid. NVIDIA's latest GPU servers dissipate over 100 kW per rack (the cabinet that holds servers), physically beyond what conventional air cooling can remove. KDDI's Osaka Sakai Data Center, live since January 22, 2026, reused the power and cooling infrastructure of the former Sharp Sakai plant to house NVIDIA GB200 NVL72 systems, compressing a build that normally takes three-plus years into about six months (KDDI).

Liquid cooling changes the building itself. Racks and piping filled with coolant are heavy, and Nikkei xTECH notes a survey-wide trend toward reinforced floor loading (the weight a floor can bear). The data centers now being built are designed AI-server-first — their specs are becoming a different species from conventional facilities. We explain why air cooling hit its limit in why AI servers can no longer be cooled by air (in Japanese).

Is there enough power? The boom's binding constraint

What decides whether all 38 projects get built is not money or land — it is electricity. According to a CRIEPI report analyzing demand projections from OCCTO (Japan's grid coordination organization), data center growth alone will add roughly 6.16 GW of peak demand by FY2034 versus FY2024 — equivalent to about six large nuclear reactors — and about 44 TWh of annual consumption (CRIEPI, 2025).

In the United States, data center power consumption has already become a source of local backlash and a political issue (70% of Americans do not want a data center next door, in Japanese). Japan's regional dispersal can be read as a preemptive move around that friction: build where renewables are abundant, deliver jobs and tax revenue locally, and go to the power source rather than waiting for grid upgrades. As we covered in why an AI data center takes three years from groundbreaking to power-on (in Japanese), the time from construction start to energization is the real bottleneck — which is why projects with secured power allocations keep gaining value.

Japan's 2026 data center construction boom marks the first phase in which the answer to "where do we build?" has changed to "wherever the electricity is." With Colt Minoh and NTT DATA TKY12 slated for 2030, the pipeline is already full five years out (Nikkei xTECH survey).

Article Summary

  • The Nikkei xTECH survey found 24 companies planning 38 data center builds and expansions between 2026 and 2030 — Japan's construction boom runs through at least 2030.
  • Five projects exceed 100 MW: Colt Minoh (130 MW, ~spring 2030), NTT DATA's Tokyo TKY12 (~200 MW, 2030+) and Tochigi TCG11 (100 MW, 2029), among others.
  • Of 35 confirmed locations, 13 are in Greater Tokyo, 9 in Greater Osaka, and 13 in regional Japan — about 40% outside the two metros, chasing power and renewables in Tomakomai, Ishikari, Yuzawa, Wakkanai, Oga and Satsumasendai.
  • More than half of planned facilities are liquid-cooling-ready; GPU heat density is changing data center design specs (cooling and floor loading) themselves.
  • The binding constraint is power: OCCTO projections imply data center growth alone adds about 6.16 GW of peak demand by FY2034. Projects that have secured power allocations get built first.
Sponsored

Frequently Asked Questions (FAQ)

Q.How many new data centers are planned in Japan?

A Nikkei xTECH survey of roughly 80 data center operators conducted in April-May 2026 (42 valid responses) found that 24 companies plan a combined 38 new builds and expansions. Openings run from 2026 through 2030. Five projects exceed 100 MW of power capacity, and more than half of the facilities support liquid cooling for the latest GPU servers (Nikkei BP, announced June 19, 2026).

Q.Where will Japan's new data centers be built?

Of the 35 projects with confirmed locations, 13 are in Greater Tokyo (including Chiba and Saitama), 9 in Greater Osaka (including Kyoto), and 13 elsewhere in regional Japan. The traditional Tokyo-Osaka duopoly is breaking up: regional sites now account for about 40%, including Hokkaido (Tomakomai, Ishikari, Wakkanai), Yuzawa in Niigata, Oga in Akita, Futaba in Fukushima and Satsumasendai in Kagoshima (Nikkei xTECH survey).

Q.Why are Japanese data centers moving to regional areas?

Power is the biggest reason. Spare grid capacity around Tokyo and Osaka has shrunk, making large power allocations hard to secure. Regional areas like Hokkaido offer renewable energy, cheaper land, and cool climates that cut cooling costs. SoftBank's Tomakomai AI data center will run on 100% Hokkaido-sourced renewables, and Kyocera Communication Systems' Ishikari site achieved Japan's first 24/7 renewable operation.

Q.What is a liquid-cooling-ready data center?

A facility designed to carry server heat away with liquid (cooling water or refrigerant) rather than air. NVIDIA's latest GPU servers generate more than ten times the heat per rack of conventional servers, beyond what air cooling can handle. In the Nikkei xTECH survey, more than half of planned facilities are liquid-cooling-ready, and operators are also reinforcing floor loading to bear the heavier equipment.

Glossary

References & Sources

  1. 【日経クロステック調査】日本では2026年以降もデータセンターの建設ラッシュ、新設・増設予定は24社の38件 地方分散の動きもPrimary source
    日経BP(プレスリリース) (2026-06-19) — Cited for: 調査概要(2026-04-23〜05-26・約80社対象・有効回答42社)・24社38件・2026〜2030年開業・東京圏13/大阪圏9/東阪外13件(所在地確定35件)・受電容量100MW超5件・液冷対応半数超・床荷重強化の傾向
    https://www.nikkeibp.co.jp/atcl/newsrelease/corp/20260619/
  2. 2026年以降開業のデータセンターを独自調査、受電容量や液冷方式を一挙公開News media
    日経クロステック (2026-06) — Cited for: 38件の回答一覧表(企業名・施設名・所在地・延べ床面積・ラック数・受電容量・開業時期)。Colt箕面130MW(IT)2030年春頃・Colt吉川80MW(IT)・NTTデータ栃木TCG11 100MW/東京TKY12 200MW・SC Zeus OSA1 100MW超・STT Tokyo 2 60MW・KDDI大阪堺最大48MW・東急不動産石狩15MVA等の個別数値
    https://xtech.nikkei.com/atcl/nxt/column/18/03615/060300003/
  3. 次世代社会インフラ構想実現への第一歩。最先端のAI基盤を搭載する日本最大級「北海道苫小牧AIデータセンター」起工式Primary source
    ソフトバンク(公式) (2025-04-21) — Cited for: 苫小牧AIデータセンター=敷地約70万㎡・将来受電容量300MW超の国内最大級・2026年度開業目標・北海道内の再エネ100%を利用する地産地消型
    https://www.softbank.jp/sbnews/entry/20250421_01
  4. シャープ堺工場を活用した大規模なAIデータセンターの構築についてPrimary source
    ソフトバンク(公式) (2024-06-07) — Cited for: ソフトバンクがシャープ堺工場の土地・建物(敷地約44万㎡)を取得して大規模AIデータセンターへ転用する計画の一次発表
    https://www.softbank.jp/corp/news/press/sbkk/2024/20240607_01/
  5. 大阪堺データセンターを1月22日から稼働開始Primary source
    KDDI(News Room) (2026-01) — Cited for: KDDI大阪堺データセンター2026-01-22稼働・シャープ堺工場跡地の電力/冷却設備を再利用し通常3年以上の構築を約半年に短縮・NVIDIA GB200 NVL72収容・KDDI GPU Cloud提供開始
    https://newsroom.kddi.com/news/detail/kddi_nr-891_4287.html
  6. 関西地域に30MWの「京阪奈OSK11データセンター」を開設Primary source
    NTTデータグループ(公式) (2026-04-09) — Cited for: 京阪奈OSK11(京都府精華町)=IT容量30MW・サーバールーム約1万900㎡・Tier III相当・AI/クラウド需要対応の次世代設計
    https://www.nttdata.com/global/ja/news/topics/2026/040900/
  7. NTTデータグループ、印西・白井にデータセンターを新設へ 2030年以降の提供開始目指すNews media
    EnterpriseZine (2026) — Cited for: 東京TKY12=印西・白井エリアの総IT容量約200MW・6棟構成キャンパス型・第1期棟2030年以降サービス開始
    https://enterprisezine.jp/news/detail/24163
  8. 京セラコミュニケーションシステム、ゼロエミッション・データセンター石狩を開所Primary source
    京セラコミュニケーションシステム(公式) (2024-10-01) — Cited for: ZED石狩=石狩湾新港洋上風力+自社太陽光による生グリーン電力運用・蓄電池とAI需給制御で国内DC初の常時再エネ100%(24/7カーボンフリー)
    https://www.kccs.co.jp/news/release/2024/1001/
  9. GPUデータセンターとクラウドサービスを展開するハイレゾ社への出資Primary source
    豊田通商(公式) (2025-07-04) — Cited for: 豊田通商のハイレゾ出資。ハイレゾは石川県志賀町・香川県高松市でAI開発用GPU専用データセンターを運営(男鹿・綾川の新設計画の背景)
    https://www.toyota-tsusho.com/press/detail/250704_006635.html
  10. ゲットワークスとGXテクノロジー、液冷採用のコンテナ型データセンター「湯沢GXデータセンター」を本格運転開始News media
    クラウドWatch (2026-02) — Cited for: 湯沢GXデータセンター運転開始・新潟県湯沢町でコンテナ約110棟規模・液冷コンテナ型GPUデータセンターの地方展開
    https://cloud.watch.impress.co.jp/docs/news/1665293.html
  11. データセンターの電力需要の特徴に関する考察と将来推計Research firm
    電力中央研究所(SERC25001) (2025) — Cited for: OCCTO需要想定の整理=データセンター新増設分で2034年度に最大需要電力約616万kW・年間需要電力量約440億kWh増加(2024年度比)
    https://criepi.denken.or.jp/jp/serc/research/files/1674/pdf/serc25001.pdf

Share This Article

Comments

Sign in with your GitHub account to leave a comment.