Latest updateAugust 9, 2026Chips Took 8 Days, Cars Took 22 — The Kumamoto Earthquake Wrap-Up, and Why the Buildings Weren't What Split the Recovery
Just 30 hours after the earthquake, on the night of July 29, the Nishiki plant (Nishiki Town, Kuma District) — one of Renesas's Kumamoto fabs — had already resumed production. Sony Semiconductor Solutions' Kumamoto Technology Center (Kikuyo Town), by contrast, still had no restart timeline as of the morning of July 31, day four. Though struck by the same earthquake, what split the recovery in two was what was inside the buildings — whether cleanroom conditions had held up in the immediate aftermath.

[July 31 evening update] Sony, which this article had identified as the "only operator without a restart plan," disclosed its recovery plan in an official second statement dated July 31. The Kumamoto Technology Center (Kikuyo Town) said that, "having completed safety checks and recovery work on the building and equipment," it "plans to resume operations progressively from Tuesday, August 4," and "expects to return to pre-earthquake production levels by mid-August." The silence was broken on the afternoon of day four. Tokyo's market close saw the Nikkei average surge 2,494 points, with chip stocks rising broadly, but the main driver cited for the close was a reassessment following strong US tech earnings, and no link to Kumamoto's earthquake recovery has been confirmed (Sony Semiconductor Solutions; Jiji Press, July 31, 2026). The body text below reflects the state of things as of the morning of July 31; subsequent updates have been appended at the end of each relevant section.

[July 31 night update] For the first time at a Kumamoto semiconductor site, a plant has returned to "pre-earthquake production capacity." In its third statement on July 31, Renesas said the Nishiki plant "resumed production progressively from the night of July 29, and returned to pre-earthquake production capacity this morning." The Kawajiri plant, too, plans to return to pre-earthquake production capacity "within about three weeks" of its August 5 restart. The impact on automobiles, meanwhile, has only widened. Toyota disclosed it would halt its Tahara plant in Aichi Prefecture from August 3 to 7, and Honda extended the halt at its Kumamoto plant through August 7. The cause is that Aisin Kyushu, in Kumamoto City, was damaged in the quake and has cut off the supply of key car-door components. One industry's machines are starting up again while the other's stay silent — on day four of the same earthquake, the clocks of two industries are running in opposite directions (Renesas official statement; Jiji Press, July 31, 2026).

This article organizes the situation as of the morning of July 31 — day four of the earthquake — following our day-3 update from midday July 30. Please also see our day-2 follow-up from July 29 and our initial status report from the night of the quake, July 28. Between the night of July 29 and the morning of July 31, a string of developments emerged: Renesas's Nishiki plant restarting, details of Mitsubishi Electric's partial restart, and a third-party analyst's estimate of the impact on TSMC subsidiary JASM. Building on these, this article organizes the situation around two questions: "why did the recovery speed split so sharply?" and "if the impact is small, is it safe to relax?"

In Plain Terms (Beginner)

On the night of day three after the earthquake, a Renesas plant called Nishiki started moving again — just 30 hours after the quake. The reason: the air conditioning and power inside the factory's 'cleanroom' (a super-clean room) never stopped. Sony's Kikuyo plant, though, was still in an 'we don't know when we can restart' state even on the morning of day four. Experts calculate that the impact on TSMC's Kumamoto plant is only about 0.03% for the whole company, but chips used in cars can't quickly be replaced by another factory's output, so it's not something to shrug off. The number of dead rose to 35 (as of 9:40 a.m. on July 31). Sony's Kikuyo plant also announced on the evening of July 31 that it will 'restart a little at a time from August 4, and get back to normal by mid-August.' On the morning of July 31, Renesas's Nishiki plant got back to a state where it can make just as much as before the earthquake — the first full comeback among Kumamoto's semiconductor plants. Cars are the opposite story, though: because a parts factory in Kumamoto was damaged, even Toyota's plant in Aichi Prefecture is having to stop from August 3 to 7.

Also see: The Structural View (Investor)
The Structural View (Investor)

Verified status as of the morning of July 31: (1) Renesas — official second statement (issued 5:18 p.m., July 30): the Nishiki plant has already been resuming operations progressively since the night of July 29, and the Kawajiri plant is scheduled to resume progressively from August 5 (a plan only, not confirmed). Sustained cleanroom air conditioning and power was the condition that enabled the early restart (per Renesas's statement). (2) Sony — its official notice dated July 29 remained the latest as of the morning of July 31. Nikkei (filed 5:00 a.m., July 31) reported 'Sony taking time to confirm damage,' positioning it as the only major Kumamoto operator without a restart plan. (3) JASM — no fourth statement as of the morning of July 31 (the third statement, issued 8:47 p.m. Taiwan time on July 29, remains the latest state). DIGITIMES analyst Huang Chien-chih's estimate (July 30, via CNA) puts worst-case revenue exposure at about US$14 million — roughly 0.03% of TSMC's Q3 revenue guidance midpoint of $45.2 billion — though this is a third-party estimate, not TSMC's own disclosure. The same analyst noted that automotive and specialty chips cannot be shifted to another fab in the short term because of customer qualification requirements. (4) Mitsubishi Electric — both its Koshi and Kikuchi plants sustained no major building damage and have resumed operations progressively from equipment cleared as safe; the timeline for a full restart remains undecided (Kumamoto Nichinichi Shimbun, 7:59 p.m., July 30). (5) Tokyo Electron Kyushu — no major damage at either site, planning a full production restart from August 3 (per Yomiuri Shimbun). (6) Ports — the Ministry of Land, Infrastructure, Transport and Tourism's tenth report (as of 7:30 a.m., July 31) found rail damage and an oil leak at Yatsushiro Port's container crane, with repair options under review (the quay wall itself was separately judged fit to berth vessels in the early hours of July 30 — a distinct issue). (7) Earthquake and society — aftershocks of intensity 5-lower or greater totaled five as of 5 p.m. on July 30, with none since the M5.8 quake at 10:19 p.m. on July 29 through the morning of July 31. The death toll stood at 35, including cases still under review, as of 9:40 a.m. on July 31. Toyota's three Kyushu plants and Honda's Kumamoto plant remain halted through July 31 with no change, and Nissan's Kanda plant was partially halted from the afternoon of July 30 through July 31. (8) Markets — in the July 31 morning session, the Nikkei average rose 2,704 points to 64,572.25, briefly up more than 3,400 points, reported as 'chip-stock buybacks' (Jiji Press, 11:41 a.m./12:16 p.m.). Renesas rose 7.51% to 3,436 yen (as of 1:29 p.m.), though no commentary has tied this to recovery progress; Sony Group rose 0.26%, likely mainly on its Q1 earnings released the same day (operating profit +40.2%). An 'extremely severe disaster' designation remained unconfirmed as of the afternoon of July 31. [July 31 evening update] Sony's official second statement: Kikuyo will resume operations progressively from August 4, expected back to pre-earthquake levels by mid-August (resolving the 'only operator without a restart plan' status). At the close, the Nikkei average was up 2,494 points at 64,362.02, with chip stocks surging — Advantest +16.34%, Disco +12.74%, Tokyo Electron +6.24%, Renesas +7.70%, SCREEN +5.18% (mainly attributed to strong US tech earnings; no link to earthquake recovery has been confirmed) — while Sony Group fell 0.58%. Death toll: 35 (as of 9:40 a.m.). The severe-disaster designation and the status of auto plants from August 1 onward both remained unconfirmed as of the evening. [July 31 night update] Renesas's third statement: the Nishiki plant returned to pre-earthquake production capacity on the morning of July 31 (the first full comeback among Kumamoto's fabs), and Kawajiri aims to reach pre-earthquake capacity within about three weeks of its August 5 restart. The automotive impact has widened — Aisin Kyushu's damage cut off the supply of door components, halting Toyota's Tahara plant (Aichi) from August 3-7, extending the halt at Toyota Motor Kyushu's three plants (no end date given), Honda's Kumamoto plant through August 7, Daihatsu Kyushu through August 5, and Nissan's two Fukuoka plants as well. Death toll: 36, with more than 9,000 evacuated (as of 8:53 p.m.). Kyushu Shinkansen service between Kumamoto and Shin-Minamata now looks unlikely to resume within August. Both JASM's fourth statement and the severe-disaster designation remained unconfirmed as of that night. [Correction, August 1 update] Government primary sources (Fire and Disaster Management Agency's 26th report; the Prime Minister's disaster-response meeting) put the toll at 35 as of August 1, unchanged from the previous report — the 36 figure traces to Jiji Press and has not been confirmed in primary sources.

Why could the Nishiki plant restart within 30 hours?

Renesas Electronics issued its second official statement since the earthquake at 5:18 p.m. on July 30. According to the statement, the Nishiki plant (Nishiki Town, Kuma District), after completing cleanroom safety checks, has been resuming production progressively since the night of July 29 — about 30 hours after the earthquake struck (per Renesas's official statement, 5:18 p.m., July 30, 2026).

The reason the plant could restart so quickly is that, even with damage such as some ceiling panels falling and cracked walls, its air conditioning and power supply held up, and the cleanliness of the cleanroom itself — a particle-controlled clean space — was preserved. As explained in our previous update, when a cleanroom's air conditioning and power hold up, a fab doesn't need to redo its "cleanroom certification" — the process of confirming particle-concentration and other standards are met — and recovery is that much faster. The Nishiki plant's 30-hour restart is exactly this structure playing out.

Meanwhile, Renesas's other Kumamoto plant, Kawajiri (Minami-ku, Kumamoto City), was announced as scheduled to resume production progressively from August 5 (per Renesas's official statement, 5:18 p.m., July 30, 2026). This, too, is only a plan — not a confirmed date. As the word "progressively" suggests, neither plant is returning to full operation all at once; both continue a staged startup. Kumamoto Nichinichi Shimbun reported the same details in its 10:16 p.m. filing on July 30 (Kumamoto Nichinichi Shimbun, July 30, 2026).

Mitsubishi Electric shows a similar pattern. Its Koshi and Kikuchi plants are "operating equipment progressively, from the equipment cleared as safe, with no major damage to the buildings," and there have been no employee injuries (Kumamoto Nichinichi Shimbun, 7:59 p.m., July 30, 2026). Still, only some processes have restarted, and the timing of a full restart remains undecided. Tokyo Electron Kyushu, too, is reported to have sustained no major damage to buildings or equipment at either its Koshi or Otsu sites, and plans to resume full production from August 3 (Yomiuri Shimbun, July 30, 2026). Even where "the building is intact" and "restart is progressive" hold in common, how far each company has come in restoring its processes still varies.

[July 31 night update] On July 31, Renesas issued its third official statement since the earthquake, titled "Impact of the 2026 Kumamoto Earthquake on Our Business Activities (Third Report)." Verbatim, it states that the Nishiki plant "resumed production progressively from the night of July 29, and returned to pre-earthquake production capacity this morning." The progressive restart that began on the night of July 29 reached full pre-earthquake production capacity in roughly a day and a half, by the morning of July 31 — the first Kumamoto semiconductor site to reach that milestone. As for the Kawajiri plant, the statement says it is "scheduled to resume production progressively from August 5," and Renesas aims to bring it back to pre-earthquake production capacity (on a production-start basis) "within about three weeks" of that restart (Renesas's official third statement, July 31, 2026). Where the Nishiki plant's 30-hour restart was a measure of "how fast a fab can start moving again," this third statement points to the next benchmark: how fast it can climb back to its original capacity once it has restarted — a process the Kawajiri plant has yet to go through.

Why was Sony's Kikuyo plant alone still silent on day four?

As of the morning of July 31, Sony Semiconductor Solutions' most recent official notice was still the one dated July 29. Its Kumamoto Technology Center (Kikuyo Town) has halted production, and the notice — which said it was still checking the condition of buildings and facilities — made no mention of a restart timeline (Sony Semiconductor Solutions, official notice dated July 29, 2026).

Nikkei, in an article filed at 5:00 a.m. on July 31, ran the headline "Renesas, Tokyo Electron resume production progressively in Kumamoto; Sony taking time to confirm damage," reporting that Sony was the only one of Kumamoto's major operators still without a restart timeline (Nikkei, filed 5:00 a.m., July 31, 2026).

No specifics about the damage or a restart timeline have yet been given, and this article does not speculate about the damage or state anything as fact beyond what's confirmed. What is known is only this: as of the morning of July 31, Sony alone was left behind. Within the same earthquake and the same four days, one plant is running and another still cannot run — and that gap itself is the single most important thing to understand about how this Kumamoto earthquake's recovery has unfolded.

[July 31 evening update] Sony Semiconductor Solutions issued an official second statement dated July 31, titled "On the impact of the 2026 Kumamoto earthquake (second report)." Verbatim, it says: "Having completed safety checks and recovery work on the building and equipment, we plan to resume operations progressively from Tuesday, August 4. We expect to return to pre-earthquake production levels by mid-August." It gives no specific description of damage (Sony Semiconductor Solutions, July 31, 2026). No timeline had been given on the morning of day four, but a restart plan emerged that same afternoon. Sony's silence, it turns out, did not mean it "couldn't recover" — it meant the company was taking time over damage confirmation and recovery work. With this, every major Kumamoto operator has now either restarted or announced a restart date (with the exception of JASM's declaration of full recovery).

If the impact is only 0.03%, is it safe to relax?

DIGITIMES analyst Huang Chien-chih, in a report filed at 11:14 a.m. on July 30 (Taipei, distributed via CNA), estimated that even in a worst-case scenario where JASM halts for a full week and recovers none of that lost production, the impact on revenue would be limited to about US$14 million. That is just about 0.03% of TSMC's Q3 2026 revenue guidance midpoint of $45.2 billion (official range $44.6-45.8 billion), disclosed at its July 16 earnings call (CNA, July 30, 2026). It bears noting, though, that this is a third-party analyst's estimate — not a figure TSMC itself has disclosed.

Huang attached conditions to this estimate. The biggest variable determining how fast equipment can restart, he said, is the frequency of aftershocks, and he pointed out that automotive and specialty-use chips go through customer-specific qualification — the process of confirming a part meets required specifications — before use, meaning they cannot be substituted with output from another fab in the short term (CNA, July 30, 2026; Taipei Times, July 31, 2026). In other words, the "0.03% impact" figure assumes products that can be substituted; it does not apply as-is to automotive or specialty chips.

A companion piece on why semiconductor capacity is so concentrated in Kumamoto in the first place — and which products do or don't have a backup factory elsewhere makes the same point: substitutability varies sharply by site and by product. Set alongside the redundancy assessment from our initial status report on the day of the quake, a structure emerges: JASM itself would normally rank "high" for substitutability, but the constraint of automotive qualification partially cancels out that rating. This isn't something the size of a single number alone can put to rest.

TSMC subsidiary JASM had issued no fourth statement as of the morning of July 31. The state described in its third statement — issued at 8:47 p.m. Taiwan time on July 29, noting that equipment inspection and recalibration was continuing and that full recovery had not been declared — remains unchanged (Taipei Times, TechNews, July 31, 2026). Note also that the seismic intensity actually recorded at JASM's Kikuyo site was 5-upper (per TSMC's own statement), distinct from the intensity 7 recorded in Uki City and Hikawa Town. It's worth reiterating here, too, that a partial restart and full recovery are separate concepts.

[July 31 night update] This section's point — that automotive chips can't be quickly substituted because of customer qualification requirements — was borne out on the night of July 31 in the form of automobiles themselves grinding to a halt. Per Jiji Press (filed 8:02 p.m., July 31), Aisin Kyushu (Kumamoto City) — an automotive-parts maker, not a semiconductor maker — was damaged in the quake and has halted production of key car-door components. This single parts plant's shutdown has now halted Toyota's Tahara plant in Aichi Prefecture from August 3 to 7, and led Toyota Motor Kyushu to further extend the halt at its three Fukuoka plants beyond the period through July 31 originally planned (the report gives no specific end date for the extension). Honda has also extended its Kumamoto plant's halt through August 7, Daihatsu has extended the halt at its two Kyushu plants through August 5, and Nissan has extended a partial halt of some models' production at its two Fukuoka plants (the same report describes this only as "through the same day," so no specific date can be pinned down). Even as recovery at the semiconductor fabs advances, the automotive halts have spread beyond Kumamoto Prefecture. A single irreplaceable part stopping is enough to halt a finished-vehicle line — and that structure isn't limited to chips.

What is the state of ports, seismic activity, and society?

According to the Ministry of Land, Infrastructure, Transport and Tourism's tenth damage report (as of 7:30 a.m., July 31), the container crane at Yatsushiro Port has sustained rail damage and an oil leak, and port operators, the crane manufacturer, and port-construction contractors are on site examining repair options. No recovery timeline has been given yet (Ministry of Land, Infrastructure, Transport and Tourism, July 31, 2026). The same report also confirms that Yatsushiro Port's container quay (12m depth, 200m long) was judged, in the early hours of July 30, fit to berth vessels for emergency transport. But "the quay can be used" and "the crane can be used" are separate matters, and the two should not be conflated.

Aftershock activity is beginning to settle. Per Japan Meteorological Agency figures (as of 5 p.m., July 30), aftershocks of intensity 5-lower or greater totaled just five, and none has occurred since the M5.8 quake at 10:19 p.m. on July 29, through the morning of July 31 (Japan Meteorological Agency, July 30-31, 2026).

The human toll continues to grow. NHK reported, in a flash bulletin as of 9:40 a.m. on July 31, that the death toll had risen to 35, including cases still under review; Kumamoto Nichinichi Shimbun (filed 10:00 a.m. the same day) reported the same figure (NHK flash bulletin; Kumamoto Nichinichi Shimbun, July 31, 2026). [July 31 night update] Per Jiji Press (filed 8:53 p.m., July 31), the death toll rose to 36 on the night of July 31, with more than 9,000 people evacuated. Jiji Press also reported, in a separate article filed at 8:25 p.m. the same day, that resuming Kyushu Shinkansen service between Kumamoto and Shin-Minamata within August now looks difficult.

[Correction, August 1 update] Subsequent primary sources put the death toll at 35 as of 7 a.m. on August 1 (Fire and Disaster Management Agency's 26th report, explicitly noting "unchanged from the previous report"), and Prime Minister Takaichi also stated at the government's disaster response meeting (July 31) that the toll stood at "35 as of 3 p.m. that day." The figure of 36 cited here came from Jiji Press (filed 8:53 p.m., July 31) and has not been confirmed in government primary sources. The latest status is covered in the Day 5 update (Fire and Disaster Management Agency, Prime Minister's Office, August 1, 2026).

In the auto industry, there's no change to the July 29 announcement that Toyota Motor Kyushu's three Fukuoka plants (Miyata, Kokura, Kanda) and Honda's Kumamoto plant would remain halted through July 31. Whether they can restart from August 1 onward was still unconfirmed as of the morning of July 31 (Nikkei, July 29, 2026). Nissan's Kanda plant (Fukuoka Prefecture) has also partially halted operations from the afternoon of July 30 through July 31, owing to damage at parts supplier Aisin Kyushu (Nikkei, July 30, 2026).

Where is market attention focused?

Tokyo's market rose sharply on July 31. The Nikkei average closed its morning session at 64,572.25, up 2,704 points from the previous day, briefly gaining more than 3,400 points. Market commentary cited "chip-stock buybacks" as the driver (Jiji Press, filed 11:41 a.m. and 12:16 p.m., July 31, 2026). This was a broad market-wide rebound, however, and no reporting has confirmed that Kumamoto's recovery progress was the main driver.

Among individual stocks, Renesas Electronics — which had announced the Nishiki plant's restart and the Kawajiri plant's planned August 5 restart the previous evening — was bought up 7.51% to 3,436 yen (as of 1:29 p.m., July 31). No commentary has explicitly tied this rise to recovery progress, though, and as of this writing it cannot be separated from the market-wide chip-stock buyback. Sony Group, meanwhile, moved little, up 0.26% at 3,819 yen (as of 1:28 p.m.), but the company released its Q1 FY2027 earnings on July 31 (revenue up 8.2% year-on-year, operating profit up 40.2%), and earnings appear to be the main driver of its stock move (Yahoo! Finance, July 31, 2026). How the Kumamoto plant's halt was factored into its earnings outlook remains unconfirmed as of this writing.

As for an "extremely severe disaster" designation, no reporting had confirmed a decision or prospect as of the afternoon of July 31. The Prime Minister's Office's chief cabinet secretary press-briefing page had not yet posted anything for July 31 (Prime Minister's Office, checked July 31, 2026). Likewise, no new announcement has been confirmed regarding Toyota's, Honda's, or Nissan's restart prospects from August 1 onward.

[July 31 evening update] At the close, the Nikkei average surged to 64,362.02, up 2,494 points from the previous day (Jiji Press, filed 3:40 p.m., July 31). Chip-related stocks also surged broadly: at the 3:30 p.m. close on July 31, Advantest rose 16.34% (32,500 yen), Disco 12.74% (58,480 yen), Tokyo Electron 6.24% (55,500 yen), Renesas 7.70% (3,442 yen), and SCREEN 5.18% (12,600 yen). Sony Group, by contrast, dipped 0.58% (3,787 yen) (Yahoo! Finance). The main driver cited for the close was reassessment buying of AI and chip stocks following strong earnings from US tech firms, and no commentary has attributed the move mainly to hopes for Kumamoto's earthquake recovery. The center of gravity behind the rally may have shifted from the morning's "chip-stock buybacks" by the close. Neither a decision on the severe-disaster designation nor new restart prospects for Toyota, Honda, or Nissan from August 1 onward had been confirmed as of the evening of July 31.

Key takeaways

  • Renesas's Nishiki plant resumed production on the night of July 29, about 30 hours after the earthquake. Sustained cleanroom air conditioning and power kept cleanliness intact, enabling the early restart (Renesas's official second statement, 5:18 p.m., July 30). The Kawajiri plant is scheduled to resume progressively from August 5, but that date is not yet confirmed. Renesas's official third statement (July 31) said the Nishiki plant had returned to pre-earthquake production capacity that morning — the first Kumamoto semiconductor site to reach that milestone. Kawajiri aims to reach pre-earthquake capacity within about three weeks of its August 5 restart (Renesas's official third statement, July 31).
  • Sony's Kikuyo plant had given no restart timeline as of the morning of July 31, but its official second statement that evening announced it "plans to resume operations progressively from August 4" and "expects to return to pre-earthquake production levels by mid-August" (Sony official statement; Nikkei, filed 5:00 a.m., July 31).
  • A DIGITIMES analyst's estimate found that even in a worst case where JASM halts for a week and recovers none of the lost output, the revenue impact would be limited to about 0.03% (roughly $14 million) of TSMC's Q3 revenue guidance midpoint. This is a third-party estimate, not TSMC's own disclosure, and automotive and specialty chips cannot be substituted in the short term because of customer qualification requirements (CNA, July 30). On the night of July 31, with Aisin Kyushu (Kumamoto City) damaged, the automotive impact spread beyond Kumamoto Prefecture: Toyota's Tahara plant (Aichi) halted August 3-7, Toyota Motor Kyushu's three plants extended their halt, Honda's Kumamoto plant halted through August 7, and Daihatsu Kyushu through August 5 (Jiji Press, filed 8:02 p.m., July 31).
  • At the ports, Yatsushiro Port's container crane suffered rail damage and an oil leak, and repair options are under review (Ministry of Land, Infrastructure, Transport and Tourism's tenth report, as of 7:30 a.m., July 31). As of 5 p.m. on July 30, there had been five aftershocks of intensity 5-lower or greater in total, and none since the M5.8 quake at 10:19 p.m. on July 29. Resuming Kyushu Shinkansen service between Kumamoto and Shin-Minamata within August now looks difficult (Jiji Press, filed 8:25 p.m., July 31).
  • The death toll rose to 35, including cases still under review (NHK, as of 9:40 a.m., July 31). Toyota's three Kyushu plants and Honda's Kumamoto plant remain halted through July 31 with no change, and Nissan's Kanda plant is also partially halted owing to a parts-supply delay. Tokyo's market on July 31 rebounded sharply — up 2,704 points in the morning session alone — and closed up 2,494 points at 64,362.02, with chip stocks surging across the board (Advantest +16.34%, Disco +12.74%, Tokyo Electron +6.24%). But the main driver was a reassessment following strong US tech earnings, not Kumamoto's recovery progress, and no reporting has drawn that connection (Sony Group ended down 0.58%). On the night of July 31, the death toll rose to 36 with more than 9,000 people evacuated (Jiji Press, filed 8:53 p.m., July 31). Primary sources (Fire and Disaster Management Agency, Prime Minister's Office) put the toll at 35 as of August 1, unchanged from the previous report.

Article Summary

  • Renesas's Nishiki plant resumed production on the night of July 29, about 30 hours after the earthquake. Sustained cleanroom air conditioning and power kept cleanliness intact, enabling the early restart (Renesas's official second statement, 5:18 p.m., July 30). The Kawajiri plant is scheduled to resume progressively from August 5, but that date is not yet confirmed. Renesas's official third statement (July 31) said the Nishiki plant had returned to pre-earthquake production capacity that morning — the first Kumamoto semiconductor site to reach that milestone. The Kawajiri plant aims to reach pre-earthquake capacity within about three weeks of its August 5 restart.
  • Sony's Kikuyo plant had given no restart timeline as of the morning of July 31, but its official second statement that evening announced it 'plans to resume operations progressively from August 4' and 'expects to return to pre-earthquake production levels by mid-August' (Sony official statement; Nikkei, filed 5:00 a.m., July 31).
  • A DIGITIMES analyst's estimate found that even in a worst case where JASM halts for a week and recovers none of the lost output, the revenue impact would be limited to about 0.03% (roughly $14 million) of TSMC's Q3 revenue guidance midpoint. This is a third-party estimate, not TSMC's own disclosure, and automotive and specialty chips cannot be substituted in the short term because of customer qualification requirements (CNA, July 30). On the night of July 31, that constraint played out in practice: with parts maker Aisin Kyushu damaged, Toyota halted its Tahara plant in Aichi from August 3-7, Toyota Motor Kyushu's three plants extended their halt, Honda's Kumamoto plant stayed halted through August 7, and Daihatsu's two Kyushu plants stayed halted through August 5 (Jiji Press, July 31).
  • At the ports, Yatsushiro Port's container crane suffered rail damage and an oil leak, and repair options are under review (Ministry of Land, Infrastructure, Transport and Tourism's tenth report, as of 7:30 a.m., July 31). As of 5 p.m. on July 30, there had been five aftershocks of intensity 5-lower or greater in total, and none since the M5.8 quake at 10:19 p.m. on July 29. Resuming Kyushu Shinkansen service between Kumamoto and Shin-Minamata within August now looks difficult (Jiji Press, July 31).
  • The death toll rose to 35, including cases still under review (NHK, as of 9:40 a.m., July 31). Toyota's three Kyushu plants and Honda's Kumamoto plant remain halted through July 31 with no change, and Nissan's Kanda plant is also partially halted owing to a parts-supply delay. Tokyo's market rebounded sharply on July 31 — the Nikkei average was up 2,704 points in the morning session alone, and at the close it finished up 2,494 points at 64,362.02, with chip stocks surging across the board (Advantest +16.34%, Disco +12.74%). But the move was mainly attributed to a reassessment following strong US tech earnings, not to Kumamoto's recovery progress, and no reporting has drawn that connection (Sony Group was down 0.58%). On the night of July 31, the death toll rose to 36 with more than 9,000 people evacuated (Jiji Press, filed 8:53 p.m., July 31). Primary sources put the toll at 35 as of August 1, unchanged from the previous report.
Sponsored

Frequently Asked Questions (FAQ)

Q.When did Renesas's Nishiki plant restart?+

The Nishiki plant (Nishiki Town, Kuma District), after completing cleanroom safety checks, has been resuming production progressively since the night of July 29 — about 30 hours after the earthquake struck (per Renesas's official second statement, announced 5:18 p.m., July 30, 2026). The Kawajiri plant (Minami-ku, Kumamoto City) is scheduled to resume production progressively from August 5, but this is only a plan, not a confirmed date. In its official third statement on July 31, Renesas said the Nishiki plant had 'returned to pre-earthquake production capacity this morning' — the first Kumamoto semiconductor site to reach that milestone. After the Kawajiri plant resumes on August 5, Renesas aims to bring it back to pre-earthquake production capacity 'within about three weeks' (Renesas's official third statement, July 31, 2026).

Q.When will Sony's Kikuyo plant restart?+

No timeline had been given as of the morning of July 31, but it emerged in the company's official second statement issued that same day. Sony Semiconductor Solutions said: 'Having completed safety checks and recovery work on the building and equipment, we plan to resume operations progressively from Tuesday, August 4. We expect to return to pre-earthquake production levels by mid-August.' (Sony Semiconductor Solutions official second statement, dated July 31, 2026). The statement does not describe specific damage. Nikkei, in an article filed at 5:00 a.m. on July 31, had reported that as of that morning Sony was the only major Kumamoto operator still taking time to confirm damage.

Q.How large is the impact on TSMC's Kumamoto fab (JASM)?+

According to a DIGITIMES analyst's estimate (July 30, 2026, distributed by CNA), even in a worst-case scenario where JASM halts for a full week and recovers none of the lost production, the impact on revenue would be limited to about 0.03% (roughly US$14 million) of TSMC's Q3 2026 revenue guidance midpoint of $45.2 billion (official range $44.6-45.8 billion, disclosed at the July 16 earnings call). This is a third-party analyst's estimate, however, not a figure TSMC itself has disclosed.

Q.If the impact is small, does that mean automotive chips are fine too?+

No, that would be the wrong conclusion. The same DIGITIMES analyst pointed out that automotive and specialty-use chips go through customer-specific qualification (the process of confirming that a part meets required specifications) before they can be used, so they cannot be substituted with output from another fab on short notice. The 0.03% estimate assumes products that can be substituted; it does not apply to automotive or specialty chips. On the night of July 31, the impact on automobiles actually widened. Jiji Press (filed 8:02 p.m., July 31) reported that Aisin Kyushu (Kumamoto City), an automotive-parts maker rather than a semiconductor maker, was damaged in the quake and halted production of key car-door components. Toyota announced it would halt its Tahara plant in Aichi Prefecture from August 3 to 7, Toyota Motor Kyushu's three Fukuoka plants extended their halt (no specific end date given in the report), Honda extended its Kumamoto plant halt through August 7, Daihatsu extended its two Kyushu plants' halt through August 5, and Nissan also extended a partial production halt for some models at its two Fukuoka plants (Jiji Press, July 31, 2026).

Q.What is the latest on the death toll and port damage from the Kumamoto earthquake?+

NHK reported, as of 9:40 a.m. on July 31, 2026, that the death toll had risen to 35, including cases still under review; Kumamoto Nichinichi Shimbun (filed at 10:00 a.m. the same day) reported the same figure. At the ports, the Ministry of Land, Infrastructure, Transport and Tourism's tenth damage report (as of 7:30 a.m., July 31) found that the container crane at Yatsushiro Port had rail damage and an oil leak, with port operators and the crane manufacturer on site examining repair options. No recovery timeline has been given yet. On the night of July 31, Jiji Press (filed 8:53 p.m.) reported the death toll had risen to 36, with more than 9,000 people evacuated (subsequent government primary sources put the toll at 35 as of August 1, unchanged from the previous report). Jiji Press also reported, in a separate article filed at 8:25 p.m. the same day, that resuming Kyushu Shinkansen service between Kumamoto and Shin-Minamata within August looks difficult.

Glossary

References & Sources

  1. 令和8年熊本地震による当社事業への影響について(第2報)Primary source
    ルネサス エレクトロニクス(公式) (2026-07-30) — Cited for: 公式第2報(30日17:18発表):錦工場(球磨郡錦町)はクリーンルームの安全確認のうえ7月29日夜から順次生産を再開済み。川尻工場(熊本市南区)は8月5日より順次生産再開予定(あくまで予定)。第1報の記載どおり、錦は天井パネル一部落下・壁ひび割れがあっても空調・電力が維持されクリーンルーム環境が保たれていたことが早期再開を可能にした
    https://www.renesas.com/ja/about/newsroom/impact-26-earthquake-kumamoto-2
  2. ルネサス錦工場、29日夜から生産再開 川尻は8月5日からNews media
    熊本日日新聞 (2026-07-30) — Cited for: 30日22:16配信:ルネサス錦工場が29日夜から順次生産再開・川尻工場は8月5日より順次再開予定と報道(公式第2報の内容と一致)
    https://kumanichi.com/
  3. ルネサスや東京エレクが熊本で生産順次再開 ソニーは被害確認に時間News media
    日本経済新聞 (2026-07-31) — Cited for: 31日05:00配信:ルネサス・東京エレクトロンなどが熊本で生産を順次再開する一方、ソニーは建屋・ファシリティの被害確認に時間を要していると報道。見出しの「ソニーは被害確認に時間」が31日朝時点の最新状況を要約
    https://www.nikkei.com/article/DGXZQOUC302OW0Q6A730C2000000/
  4. 2026年7月28日発生の熊本県熊本地方を震源とした地震の影響についてPrimary source
    ソニーセミコンダクタソリューションズ(公式) (2026-07-29) — Cited for: ソニー公式:熊本テクノロジーセンターは地震発生直後から生産活動を停止し建屋・ファシリティの被害状況を確認中・長崎/大分/鹿児島は大きな被害なし・人的被害なし・再開時期の記載なし(29日付)
    https://www.sony-semicon.com/ja/info/2026/2026072901.html
  5. 「令和8年熊本地震」の当社半導体・デバイス事業への影響について(30日付更新)Primary source
    三菱電機(公式) (2026-07-30) — Cited for: URLはmitsubishiNotice0729(29日付・操業停止発表)と同一だが、同ページが30日付で更新され部分操業再開を発表したため、29日版と30日版を区別する目的で別IDとして登録。逐語:「設備の点検および立上げ作業を進めており、設備立上げが完了した工程から順次、7月30日午後より操業を再開しております」。合志・菊池の両工場ともクリーンルーム稼働は再開済み
    https://www.mitsubishielectric.co.jp/ja/notice/2026/0729/
  6. 三菱電機、合志・菊池の両工場で一部操業再開 全面再開は未定News media
    熊本日日新聞 (2026-07-30) — Cited for: 30日19:59配信:三菱電機の合志・菊池の両工場は建屋に大きな被害はなく、安全を確認できた設備から順次動かしていると報道。従業員にけがはなく、全面再開の時期は未定
    https://kumanichi.com/articles/2019900
  7. 令和8年熊本地震について(第2報)Primary source
    東京エレクトロン(公式) (2026-07-29) — Cited for: 安全点検の結果、東京エレクトロン九州の本社(合志)・大津事業所とも建屋や設備に大きな被害なし・週明けからの生産・開発の本格稼働に向けて復旧を進める・業績への影響は軽微と判断(29日付第2報)
    https://www.tel.co.jp/news/disaster/2026/20260729_001.html
  8. 東京エレクトロン九州、8月3日から本格生産再開の方針News media
    読売新聞(Infoseekニュース) (2026-07-30) — Cited for: 30日報道:会社コメントとして、東京エレクトロン九州が8月3日から本格生産を再開する方針と伝えられた。合志・大津の両事業所とも建屋・設備に大きな被害はない(公式第2報=telKumamoto2ndの内容を踏まえた続報)
    https://news.infoseek.co.jp/article/yomiuri_20260730_gyt1t00419/
  9. JASM recovery timeline still unclear after Kumamoto quakeNews media
    Taipei Times (2026-07-31) — Cited for: 31日付:TSMC子会社JASMは7月31日朝時点で第4声明を出しておらず、7月29日20:47台湾時間の第3声明(生産設備の点検・校正作業継続中)の状態が続く。完全復旧の時期は不透明と報道。JASM菊陽の実測震度は5強(TSMC自社発表)で宇城市/氷川町の震度7とは異なる
    https://www.taipeitimes.com/News/biz/archives/2026/07/31/2003861665
  10. 熊本地震後のTSMC/JASM復旧状況News media
    TechNews(科技新報) (2026-07-30) — Cited for: 30日付:JASMは7月29日の第3声明以降、生産設備の点検・校正作業を継続中で完全復旧宣言は出ていないと報道。部分再開と完全復旧は別概念であることを整理
    https://technews.tw/2026/07/30/recovery-status-of-tsmc-jasm-after-the-kumamoto-earthquake
  11. 分析師:熊本地震對台積電營收衝擊約0.03%Research firm
    中央社(CNA) (2026-07-30) — Cited for: 30日11:14台北発:DIGITIMESアナリスト・黄健治氏の試算(第三者推計・TSMC自身の開示ではない)。JASMが1週間停止し生産を一切取り戻せない最悪ケースでも、売上曝露はTSMC第3四半期売上ガイダンス中央値452億ドル(公式レンジ446〜458億ドル・7/16決算発表)の約0.03%(約1,400万米ドル)。同氏は余震頻度が装置再稼働の最大変数とし、車載・特殊チップは顧客認証の関係で短期の他工場振替が不可能と指摘
    https://www.cna.com.tw/news/afe/202607300087.aspx
  12. 令和8年熊本地震の地震活動の関連情報Government
    気象庁 (2026-07-29) — Cited for: 気象庁特設ページ。29日昼時点の報道発表は計4件(すべて28日付)で余震見通しは変更なく継続
    https://www.jma.go.jp/jma/menu/20260728_kumamoto_jishin.html
  13. 熊本地震の死者35人に 関連調査中含むNews media
    熊本日日新聞/NHK速報 (2026-07-31) — Cited for: 31日午前9時40分時点でNHKが速報:死者は関連調査中を含め35人に増加。熊本日日新聞(31日10:00配信)も同数で一致。夕方(31日16:53〜17:29配信)の続報でも死者は35人のまま変わらず。※同経路で伝えられた負傷者126人はYahoo!ニュース集約由来で通信社本文の裏取りができず記事には不採用
    https://kumanichi.com/
  14. トヨタ3工場月内停止、半導体・飲料工場も止まる 熊本地震の影響拡大News media
    日本経済新聞 (2026-07-29) — Cited for: トヨタは29日朝に再開した福岡3工場(宮田・小倉・苅田)を29日夕方から31日まで再停止(安全・物流・仕入れ先の状況を考慮)・ホンダ熊本製作所は31日まで停止延長・サントリー熊本は国内9工場へ生産移管(29日10:43配信・16:52更新)
    https://www.nikkei.com/article/DGXZQOUC290QA0Z20C26A7000000/
  15. 日産苅田、一部稼働停止へ アイシン九州被災で部品供給遅延News media
    日本経済新聞 (2026-07-30) — Cited for: アイシン九州の被災による部品供給遅延で、日産自動車の苅田工場(福岡県)が30日午後〜31日に一部稼働停止。アイシン九州は今回で3度目の被災で、担当者は「生産設備が動くかまだ試せていない」とコメント
    https://www.nikkei.com/article/DGXZQOFD29B3M0Z20C26A7000000/
  16. 令和8年熊本地震による被害状況等について(第10報)Government
    国土交通省 (2026-07-31) — Cited for: 31日7:30時点の一次PDF。八代港コンテナクレーンにレール変状・油漏れが発生し、港運事業者・クレーンメーカー・港湾建設業者が現地入りして復旧対策を検討中(復旧時期見通しなし)。同報で八代港コンテナ岸壁(水深12m・延長200m)は7月30日未明に緊急輸送用として接岸可能と判断されたことも確認(岸壁が使えることとクレーンが使えることは別)
    https://www.mlit.go.jp/common/002014529.pdf
  17. 2016年熊本地震の半導体工場被害の記録News media
    電子デバイス産業新聞 (2016) — Cited for: 2016年の前例:クリーンルーム吊り天井の損傷で清浄機能喪失・製造装置の18%が11mm以上の位置ズレ——「揺れ自体より精密設備の位置ズレと清浄度喪失が復旧を長引かせる」根拠
    https://www.sangyo-times.jp/article.aspx?ID=2318
  18. 2704円高の6万4572円25銭 31日午前の平均株価/東京株、一時3400円超高 半導体株、買い戻しの動きNews media
    時事通信 (2026-07-31) — Cited for: 31日前場終値:日経平均6万4572円25銭・前日比2704円高、一時3400円超高。市況要因は「半導体株の買い戻し」(11:41配信・12:16配信の見出しで確認)。熊本の復旧進捗を主因とする説明は未確認・TOPIXの数値は未取得
    https://www.jiji.com/jc/list?g=eco
  19. ルネサスエレクトロニクス(6723)/ソニーグループ(6758) 株価News media
    Yahoo!ファイナンス (2026-07-31) — Cited for: 31日13:29時点:ルネサス3,436円・前日比+240円(+7.51%)。同13:28時点:ソニーG 3,819円・前日比+10円(+0.26%)。ソニーGは同日に27年3月期第1四半期決算(売上高+8.2%・営業利益+40.2%)を発表しており値動きの主因は決算とみられる。ルネサスの上昇を熊本の復旧進捗と明示的に結びつけた解説は未確認(株探はHTTP 403でアクセス不可)
    https://finance.yahoo.co.jp/quote/6723.T
  20. 令和8年熊本地震の影響について(第2報)Primary source
    ソニーセミコンダクタソリューションズ(公式) (2026-07-31) — Cited for: 公式第2報(31日付)逐語:「建屋および設備の安全確認と復旧作業を進めた結果、8月4日(火)より段階的に操業を再開する予定です。なお、8月中旬には地震発生前の稼働水準へ復旧する見込みです。」熊本テクノロジーセンター(菊陽町)が唯一の未再開組だった状態を解消。具体的な被害内容の記述はなし(推測で補わない)
    https://www.sony-semicon.com/ja/info/2026/2026073101.html
  21. 大引けは2494円高の6万4362円02銭 31日の東京株News media
    時事通信 (2026-07-31) — Cited for: 31日15:40配信:大引けの日経平均は64,362円02銭・前日比+2,494円。半導体関連が軒並み急伸したと報道。TOPIX終値は取得できず未確認
    https://www.jiji.com/jc/list?g=eco
  22. 半導体関連株 終値(アドバンテスト・ディスコ・東京エレクトロン・ルネサス・SCREEN・ソニーグループ)News media
    Yahoo!ファイナンス (2026-07-31) — Cited for: 31日15:30時点の終値:アドバンテスト+16.34%(32,500円)・ディスコ+12.74%(58,480円)・東京エレクトロン+6.24%(55,500円)・ルネサス+7.70%(3,442円)・SCREEN+5.18%(12,600円)、一方ソニーグループは−0.58%(3,787円)。大引け解説の主因は米テック好決算を受けたAI・半導体株の見直し買いで、地震復旧期待を主因とする論調は確認できていない(前場の「半導体株買い戻し」から要因の重心が移った可能性)
    https://finance.yahoo.co.jp/quote/6857.T
  23. 「令和8年熊本地震」による当社事業活動への影響について(第3報)Primary source
    ルネサス エレクトロニクス(公式) (2026-07-31) — Cited for: 公式第3報(31日発表)逐語:錦工場は「7月29日夜より順次生産を再開し、本日朝、震災前の生産能力に復帰」=熊本の半導体拠点で最初に震災前の生産能力への復帰を達成。川尻工場は「8月5日より順次生産を再開する予定」で、再開後「約3週間をめどに」震災前の生産能力(生産着工ベース)への復帰を目指す方針
    https://www.renesas.com/ja/about/newsroom/impact-26-earthquake-kumamoto-3
  24. トヨタ、愛知の工場停止 車部品の供給停滞、影響広がる―熊本地震News media
    時事通信 (2026-07-31) — Cited for: 31日20:02配信:トヨタ自動車が愛知県田原市の田原工場の稼働を8月3日から7日まで停止すると発表。トヨタ自動車九州の福岡県内3工場は29日朝にいったん稼働再開したが同日夕に再停止し、31日までの予定だった停止期間を延長(延長後の具体的な期限は記事に記載なし)。原因は自動車部品メーカーのアイシン九州(熊本市、半導体メーカーではない)が被災し、自動車のドアの重要部品の生産を停止していること。ホンダは熊本製作所(大津町)の稼働停止を8月7日まで延長。ダイハツは大分・福岡の九州2工場の稼働停止を8月5日まで延長。日産は福岡県の2工場で一部車種の生産停止を延長(記事では「同日まで」とのみ表現され具体的な日付は特定不可)
    https://www.jiji.com/jc/article?k=2026073101169&g=eco
  25. 熊本地震の死者36人、避難者9,000人超/九州新幹線 熊本―新水俣間は8月中の運行再開困難News media
    時事通信 (2026-07-31) — Cited for: 31日20:53配信:死者は関連調査中を含め36人に増加、避難者は9,000人超と報道。同日20:25配信の別記事で、九州新幹線の熊本―新水俣間は8月中の運行再開が困難との見通しを報道
    https://www.jiji.com/jc/list?g=soc
  26. 令和8年熊本地震について(第26報)Government
    消防庁 (2026-08-01) — Cited for: 8/1 7:00現在の一次PDF。死者35名「※前報から変更なし」(内訳=八代市20・宇城市2・嘉島町7・甲佐町1・氷川町4・調査中1)。避難指示対象=116,909世帯・246,540人。時事通信が31日夜に報じた死者36人は本報では確認できない
    https://www.fdma.go.jp/disaster/info/items/20260728kumamotojishin26.pdf
  27. 令和8年熊本地震非常災害対策本部(第4回会議)Government
    首相官邸 (2026-07-31) — Cited for: 7/31 17:20開催の第4回本部会議、高市総理発言の逐語。水=「医療・福祉機関や避難所向けの供給が滞ることのないように、自衛隊との連携強化やほかの自治体が保有する給水車の展開などが必要」「上下水道インフラ自体の復旧を加速するため…全国の上下水道技師の支援を斡旋」。電力=「当面の間、電源車による電力供給体制を維持してください」。燃料=「ガソリンなど燃料油の供給にも万全を期す必要があります」。人的被害=「災害との関連を調査中の方を含めて、本日15時時点で、35名となりました」。避難者=「熊本県を中心に約9,200名の方々が避難所に身を寄せておられ、『車中泊』を余儀なくされている方も多数おられる」(避難所ベースの下限値・車中泊は別途言及のみで内訳数値なし)。あわせて公表された内閣府集計(7/31 7:30現在)では避難所399か所・避難者9,637人(最大506か所・9,931人)。財政=「総額616億円の『普通交付税の繰上げ交付』を本日決定する」(対象団体数・交付日は不明)。現地対策本部は7/30に熊本県庁設置(本部長=津島副大臣)、本部会議は第1回7/28 19:49〜第4回7/31 17:20。激甚災害指定への言及なし(8/1朝時点で未確認)
    https://www.kantei.go.jp/jp/105/actions/202607/31hijoukaigi.html